| |
|
|
Q.1 |
Production under various
constraints: This was an easy question requiring calculation of
maximum contribution under various constraints in order to decide
whether to produce component A or component B. Most students were
able to calculate contribution margin per component correctly
but faltered in calculating maximum number of components that
can be produced. Many students used long mathematical equations
and had to abandon the question halfway. Simple arithmetic calculations
would have given the correct answer. Clerical errors such as wrong
use of machine hour rate etc. were common |
|
|
|
|
Q.2 |
Network diagram and
critical path: As many as 20% did not attempt this question indicating
the students’ selective preparations. Common mistakes were: |
| |
|
|
|
|
|
Mean activity time
was not calculated according to the usual formula of (o+4m+p)/6.
Some students drew 3 diagrams using optimistic, pessimistic and
most likely time estimates. |
|
|
|
|
|
|
|
Rough network diagrams
were drawn and in some cases no time duration was mentioned between
two activities. |
|
|
|
|
|
|
|
Some students mentioned
only the critical path without showing the duration of other paths. |
|
|
|
|
|
Q.3 |
It was an easy question
requiring reconciliation of budgeted contribution with actual
profit and variance analysis, but was the worst attempted. The
conceptual understanding of the relationship between various figures
was lacking. Common mistakes were as follows: |
|
|
|
|
|
|
|
A large number of
students either did not attempt the question or were unable to
even calculate the different variances. |
|
|
|
A large number didn’t
know how to reconcile the budgeted contribution and actual profit.
Most of them did not take fixed costs as a reconciling item. Some
were not very sure whether a particular
variance should be added or deducted in the reconciliation. |
|
|
|
Almost all students
laid blame on sales department for low sales volume even though
they had sold the full 800 units produced in the quarter. |
|
|
|
Many students named
the variable overhead efficiency variance as expenditure variance
and vice versa. |
|
|
|
The presentation of
the note to Managing Director was mostly poor and haphazard. |
| |
|
|
Q.4 |
The performance in
this question was good. However, the following mistakes were made
by considerable number of students: |
|
|
|
|
|
|
|
Students did not deduct
the scrap value of normal loss from total cost of input to ascertain
the cost of production per unit. |
|
|
|
|
|
|
|
The students used
a number of different methods to calculate unit cost of abnormal gain/loss whereas cost of good production
and abnormal gain/loss has the same unit cost. |
|
|
|
|
|
Q.5 |
Absorption vs. activity-based
costing (ABC): This question of 22 marks was well attempted with
70% students securing pass marks. Common mistakes noted were as
follows: |
|
|
(i) |
While making calculations
under the ABC method the students used the same machine hour rates
as given in the question for making calculations under absorption
costing; instead of making fresh calculations on the basis of
cost drivers. |
|
|
|
|
|
|
(ii) |
In part (b) the students
were required to compare the results and comment on the reasons
for the differences under the two methods. Instead, many students
just commented that ABC is a better costing method, and could
not secure any marks. |
|
|
|
|
|
Q.6 |
Calculating ROCE etc:
In this question only 19% of the students could secure passing
marks. A frequent mistake was that contribution was calculated
for one-night stay instead of two-nights stay. In fact most students
were unaware where to begin or conclude their answers. They didn’t
plan their answers and ended up doing various steps but without
co-relating one with another. |
|
|
|
|
Q.7 |
EOQ calculations:
Here the response was average. A common mistake was that in calculating total ordering costs the students
made their calculations on the basis of estimated quantity of
100,000 units instead of Actual usage of 125,000 units. |